Luxembourg City1.2 kilometres of tram tracks delivered for line extension

Christophe Hochard
The tram tracks for the current line's extension to Bonnevoie were delivered on Thursday. By July 2022 the works on the line should be completed.

Once the extension is complete, the tram will run from LuxExpo to Lycée de Bonnevoie via Pont Buchler as of September 2022.

The tracks were produced by Arcelor Mittal in Rodange and are being assembled by a Belgian company.

The new leg will include two additional stops, ""Leschte Steiwer” and “Bouneweg”.

60,000 passengers make daily use of the tram, peaking at 67,000 passengers during rush hour.