BettembourgRoadworks on Route de Peppange start 12 October

RTL Today
The works are planned to last two years, divided into two phases. In its first phase, between 20 October 2020 and 21 July 2021, works will take place between the motorway and the depot site of the Roads and Bridges Administration.

In its second phase, construction will continue from the depot site until Rue Valérie Strecken-Steffen and finish on 22 August 2022, when the new road will be made accessible.

In the meantime, residents only are permitted to use the road. A deviation via de N13/N31 is in place. More details can be found in this communication or on the municipality's website.