New railway bridgeSteel bridge over the A3 to Dudelange to be completed by July 2023

Christophe Hochard
To accommodate the new railway line between Howald and Bettembourg, a bridge over the A3 motorway is being built near the croix de Gasperich.
Nei Eisebunnsbréck
Wéinst der Neibaustreck vun der Eisebunn tëscht de Garen Houwald a Beetebuerg muss eng Bréck iwwert d'Diddelenger Autobunn installéiert ginn.

Once completed, the bridge will be around 200 meters long, 18 meters wide and weighing 5,900 tonnes, with a 40 m high arch, which is the main challenge of the construction.

Around 22 workers from a specialised Italian company are currently working on the site.

The new train line between Howald and Bettembourg will be 7 km long when finished and allow trains - especially TGVs - to go up to 160 kph.

The works should be finished by July 2023.